New Construction Phase Inspections: Foundation to Final
Foundation, framing, and final are the three points during construction where a private inspector catches what code inspections can miss. Here's how to decide which stages to buy, how many, and how to get access.

A phase inspection is a private visit you hire and pay for at a specific point during construction, separate from the inspections your local building department already performs. The three checkpoints that matter most are foundation and footing, framing before drywall goes up, and a final walkthrough before closing. Cost varies by market and inspector; no single national price applies.
This decision sits inside the broader process covered in the new-construction buyer's guide: once you've decided a private inspection is worth paying for, the next question is which stages to buy and when. If you haven't signed a contract yet, see what to check before you put down a deposit on a home that doesn't exist yet first.
What a Phase Inspection Actually Is
A phase inspection is a formally recognized scope of work, not an improvised add-on. ASHI, the American Society of Home Inspectors, publishes Auxiliary Standards of Professional Practice for Residential Predrywall Inspections, separate from its general Standard of Practice, which treats staged construction inspections as their own defined category.
How It Differs From Code Inspections
Your builder already has to pass inspections from the local building department at each major stage of construction. A phase inspection is different: it is a private visit you arrange and pay for, giving you, not the jurisdiction or the builder, direct visibility into the work.
Neither ASHI's nor InterNACHI's standards of practice determine code compliance. A passed municipal inspection and a private phase inspection are not substitutes for each other.
A Distinct, Named Service
ASHI's general Standard of Practice defines the scope of a typical home inspection (structural, exterior, roofing, plumbing, electrical, heating and cooling, interiors) for buildings with four or fewer dwelling units, and directs the inspector at readily accessible, visually observable, installed systems and components. InterNACHI's Standards of Practice similarly define a general home inspection as a non-invasive visual exam of accessible areas designed to identify material defects.
Neither general standard sets timing tied to a construction stage. ASHI publishes the Predrywall auxiliary standard separately for that, with its own inspection-timing rules.
The Three Stages That Matter Most
This article organizes the decision around three points: foundation and footing, framing before drywall, and a final walkthrough. That structure is not arbitrary. Federal underwriting rules for FHA-financed new construction name exactly those three stages, footing, framing, and final, as the inspection set a lender's file can rely on.
| Stage | When it happens | What gets checked |
|---|---|---|
| Foundation and footing | Before backfill covers the exterior wall | Footings, walls, fasteners, columns, slabs, waterproofing, drains |
| Framing (pre-drywall) | After structure, rough-ins, and windows/doors are installed, before drywall | Structural framing, rough-in plumbing/electrical/HVAC, and any foundation components still visible |
| Final | Before closing | General home-inspection scope: structural, exterior, roofing, plumbing, electrical, HVAC, interiors |
Foundation and Footing
ASHI's Predrywall Standard checklist includes foundation components: footings, walls, fasteners, columns, slabs, waterproofing, and drains. It scopes the work to the visible parts of those components, and says inspectors are not required to report on anything not installed, visually observable, or readily accessible. Once backfill goes in around the exterior foundation wall, that surface is no longer visible, and backfill can land well before the pre-drywall visit.
Before backfill covers it up, it's also the last easy moment to confirm the foundation actually sits where the recorded plat allows; see what a subdivision plat's easements and setback lines can block you from building for what those lines mean for a foundation placed too close to one.
Framing (Pre-Drywall)
The Predrywall standard scopes its inspection to the point after foundation components, floor, wall, and roof structural components, plumbing, electrical, and rough-in components, and windows and exterior doors are installed, and it inspects HVAC components and distribution ducts as their own section. That is the last moment all of those systems are visible at once before the walls close over them. For the full room-by-room checklist at this stage, see the full pre-drywall walkthrough checklist.
Final
A final-stage visit, ordered close to closing, typically follows the scope of a general home inspection, the kind ASHI's and InterNACHI's general standards define: structural, exterior, roofing, plumbing, electrical, HVAC, and interiors.
Roof-Deck and Connection Checks
A standard phase inspection under ASHI's or InterNACHI's standards does not specifically evaluate wind or storm resilience. If you are pursuing a resilience certification, or your insurer offers a premium credit tied to one, a program like IBHS's FORTIFIED Home adds checks beyond a typical phase inspection's scope.
What an Independent Evaluator Verifies
FORTIFIED Roof, the program's roof-level designation, requires beyond-code upgrades addressing three main vulnerabilities: roof deck-to-house connections, roof edges, and gaps in the roof deck. FORTIFIED Evaluators are independent, third-party contractors who document and verify the construction process. Eligible structures include single-family detached homes, two-family dwellings, manufactured homes built after 1994, and townhouses where each unit runs foundation to roof.
The Continuous Load Path
At the Gold level, FORTIFIED requires an engineered continuous load path: a specific plan for how the roof is fixed to the walls and how the walls are anchored to the foundation. IBHS testing shows that switching roof-deck attachment from common smooth nails to 8D ring-shank nails, and decreasing the space between nails, can double the uplift a roof can withstand.
Deciding How Many to Buy
No inspection standard and no building code tells you how many private visits to buy. Frame the decision around the three checkpoints federal underwriting policy already recognizes (footing, framing, final), and let budget and your builder's schedule decide how many of the three you book.
If You Can Only Pay for One
Framing (pre-drywall) closes over the most systems at once. The Predrywall standard's checklist covers structural framing, plumbing, electrical, and HVAC components, and windows and doors, all at the same visit, plus foundation components if backfill has not happened yet. That is the widest coverage a single visit can get you, though it is not a substitute for the other two.
Timing the Foundation Visit Separately
The exterior foundation wall is only visible before backfill, and backfill can happen well before the pre-drywall stage. A single pre-drywall visit will not necessarily catch it. Ask your builder specifically when backfill is scheduled if you want that window covered on its own.
Getting Access to the Job Site
Site access for a private inspector is not automatic. ASHI's Predrywall Standard is written around a client who hires the inspector directly, and it states the client must schedule the inspection with the builder and obtain permission for the inspector to enter the property.
Why Access Isn't Automatic
A builder's job site is an active work site under the builder's control. Nothing in ASHI's or InterNACHI's standards obligates a builder to allow entry, and ASHI's Predrywall Standard assigns the job of obtaining that permission to the client, so access has to be arranged separately, by you.
Put It in the Contract
Raise phase-inspection access before you sign, and get the builder's agreement to it in writing, ideally as part of your purchase contract, rather than assuming a verbal understanding will hold once framing starts.
Loan Type and Required Inspections
Only one loan type has a sourced staged-inspection rule: FHA. For FHA-insured Proposed Construction, the mortgagee must obtain either a building permit and certificate of occupancy, or three inspections (footing, framing, and final) performed by an ICC Residential Combination Inspector or Combination Inspector on HUD's Compliance Inspection Report (form HUD-92051), or by the local authority with jurisdiction over the property.
FHA's Rule, Specifically
This is a requirement on the lender's case file, not a mandate that you personally hire an inspector. Separate documents also have to go in the binder: form HUD-92541, Builder's Certification of Plans, Specifications, and Site, and form HUD-92544, Warranty of Completion of Construction, regardless of which inspection path the lender uses.
What This Article Doesn't Cover
VA, USDA, and conventional-loan-specific staged-inspection rules were not verified for this article and are not covered here. If you are financing with one of those programs, ask your lender directly what documentation it requires from the builder.
Why the Checklist Varies by Location
ICC announced back in 2007 that its model I-Codes had been adopted in all 50 states and Washington, D.C., and says more than 21,000 jurisdictions enforce the International Codes. Adoption happens jurisdiction by jurisdiction, though, so the exact code edition, local amendments, and the specific number and naming of required inspections are set locally, not nationally.
A Worked Example: Clark County, NV
- No temporary certificate of occupancy for single-family homes. In Clark County,
Nevada, a building has to be a commercial or multi-tenant residence to apply for a temporary CO; single-family residences and town-homes are not authorized for that temporary use.
- Drywall over unapproved framing needs sign-off. Placing drywall on one side of a
stud wall before the framing inspection is not, in the county's words, a typical construction practice. It requires prior authorization, and only with justification.
Confirm With Your Local Department
Clark County's rules are one real jurisdiction's example, not a national default. Confirm the exact inspection sequence and terminology with your own local building department before you plan a budget or a schedule around any list, including this one. The full sequence of permits and inspections from contract to closing covers the broader timeline these local inspections sit inside.
What Phase Inspections Cost
Why This Article Skips a Price
Neither the federal agencies nor the inspection standards bodies cited here publish a fee schedule for phase or predrywall inspections, so this article will not cite a dollar figure or range. Treat any specific number you see elsewhere as one local quote, not a national rate.
What Actually Drives the Cost
- Number of visits. Booking foundation, framing, and final separately costs more
in total than paying for a single visit.
- Your market. Local labor rates and inspector demand vary by region.
- Inspector credentials. ASHI or InterNACHI affiliation and any additional
certifications are worth asking about when you compare quotes side by side.
Get quotes directly from a few local ASHI- or InterNACHI-affiliated inspectors before you commit to a schedule.
The Bottom Line
A phase inspection buys visibility your builder's own code inspections do not guarantee: someone working for you, not the jurisdiction or the builder, looking at the work before it gets covered up. Pick your stages around budget and your builder's schedule, put site access in writing, and confirm the sequence with your own building department rather than assuming a single national list applies.
For the case for hiring one at all, see why a brand-new house still needs its own inspection. For what happens after you close, see what the builder's 1-2-10 warranty covers after you close. If you want help finding someone who has walked new-construction sites before, get matched with an agent who has walked new-construction sites before.
Before the foundation stage, it's worth knowing whether your lot's soil is expansive and what a geotechnical report actually adds over the free county-level tools. And if a phase inspection turns up something you want changed, confirm where the cutoff falls for revising your floor plan before you ask.
Frequently asked questions
- What's the difference between a phase inspection and my local building department's inspection?
- A phase inspection is a private visit you arrange and pay for. The building department's inspection checks the work against the locally adopted code. Both ASHI's Predrywall Standard and the general standards of practice explicitly exclude code-compliance determination from a private inspector's job, so passing one says nothing about the other.
- How many phase inspections should I pay for?
- There's no fixed rule. Frame it around the three checkpoints federal underwriting policy already recognizes (footing, framing, final) and let your budget and the builder's schedule decide how many of the three you book.
- Can I bring my own inspector onto the builder's job site?
- Yes, as a private arrangement, but it has to be negotiated with the builder and confirmed in writing, ideally in your purchase contract. ASHI's Predrywall Standard puts the scheduling and access burden on the client, not on an automatic right.
- Is my foundation inspected before or after the dirt goes back around it?
- Foundation components are part of ASHI's Predrywall Standard scope, but the exterior foundation wall is only visible before backfill, which can happen well before the pre-drywall visit. Ask your builder specifically when backfill is scheduled if you want that window covered.
- Does financing with an FHA loan require extra inspections during construction?
- For FHA specifically, yes: the lender's case file needs either a building permit and certificate of occupancy, or three staged inspections (footing, framing, final), plus a builder's certification and warranty. That's a lender documentation requirement, not the same thing as your own private inspection. VA, USDA, and conventional loans weren't verified for this article.
- Do all cities and counties require the same inspections?
- No. ICC says more than 21,000 jurisdictions enforce the International Codes, but adoption and enforcement are local, so the exact sequence and names vary. Clark County, Nevada, for example, doesn't allow a temporary certificate of occupancy for single-family homes, and says placing drywall on one side of a stud wall before the framing inspection isn't typical practice and needs prior authorization with justification. Those are that jurisdiction's rules, not a national default.
Sources
- FHA Single Family Housing Policy Handbook 4000.1, II.A.8 Programs and Products - New Construction, U.S. Department of Housing and Urban Development (HUD/FHA) Official source
- Auxiliary Standard of Professional Practice for Residential Predrywall Inspections, American Society of Home Inspectors (ASHI) Industry research
- Standard of Practice, American Society of Home Inspectors (ASHI) Industry research
- Standards of Practice for Performing a General Home Inspection, International Association of Certified Home Inspectors (InterNACHI) Industry research
- I-Codes adopted in all 50 states and Washington, D.C., International Code Council (ICC) Industry research
- Building Department Inspections FAQ, Clark County, Nevada (Department of Building & Fire Prevention) Official source
- Frequently Asked Questions, Insurance Institute for Business & Home Safety (IBHS) - FORTIFIED program Industry research
- FORTIFIED Gold, Insurance Institute for Business & Home Safety (IBHS) - FORTIFIED program Industry research