New-Home Construction Stages: Contract to Occupancy

A to-be-built home moves through a fixed sequence of permits and inspections before you can move in. Here's what happens at each stage, and where you actually get a say.

A site superintendent standing in the unfinished hallway of a house under construction, wearing a hard hat drawn as a flat illustrated money-green hard hat

A new-construction home moves through a fixed legal sequence, not just a builder's calendar: permit issuance, foundation, rough-in inspections, a frame-and-masonry inspection, interior finishes, a final inspection, and a certificate of occupancy. Under the model building code, a home cannot legally be used or occupied until that certificate is issued.

That sequence matters to you as a buyer because of one rule: no work may go past the point covered by each successive inspection until the building official approves it, and the plumbing, mechanical, gas, and electrical rough-ins have to be inspected before anything covers or conceals them. That rule creates your two real windows to see inside the house: the pre-drywall walkthrough and the final walkthrough before closing.

The baseline stages, in order:

  • Permit issued, required before construction can legally begin.
  • Foundation inspection, after excavation, forms, and reinforcing steel are in place, before concrete is poured.
  • Rough-in inspections of plumbing, mechanical, gas, and electrical systems, before they're covered and before fixtures go in.
  • Frame-and-masonry inspection, only after the rough-ins are approved.
  • Interior finishes, including drywall, paint, flooring, and fixtures, plus any additional inspections your local building department requires.
  • Final inspection, after all permitted work is complete.
  • Certificate of occupancy, required before anyone can legally live in the home.

For the full picture of buying new construction, see the new-construction buyer's guide.

Why You Might Skip Most of These Stages

If you're buying a spec or quick-move-in home that's already framed or finished, the earlier inspections happened before you ever signed a contract, so you won't see them. Only buyers who go under contract on a to-be-built home move through the full sequence below.

Either way, you're most likely buying from a builder rather than commissioning your own. In 2025, roughly 675,000 of about 940,000 single-family housing starts were built for sale, versus 131,000 built by a contractor on the owner's land and 55,000 owner-built, per the Census Bureau's New Residential Construction survey. The remainder were single-family homes built for rent, which the survey doesn't break out separately.

Census counts a home as built for sale whether it sold before the slab was poured or long after it was finished. That split tells you who the builder answers to, not how much of the build you personally see.

2025 single-family housing starts by purpose
Built-for-sale675,000homes
Contractor-built131,000homes
Owner-built55,000homes

U.S. Census Bureau / HUD, New Residential Construction, 2025 annual (revised) data. Total single-family starts were about 940,000; the balance is single-family homes built for rent, which the survey doesn't show separately by purpose.

If you haven't settled on new construction yet, it's worth comparing new construction vs. resale before you go further. And for a sense of how long each phase actually takes, see how long it takes to build a house; this article covers what happens at each stage and when you're involved, not how many weeks it takes.

Contract, Deposit, and Permits

Once you sign a purchase agreement and put down your deposit, the builder applies for a building permit, which is required before construction can legally start. Before you sign, it's worth understanding bringing your own agent to the build and negotiating incentives before you sign, since both are easier to arrange before contracts are final.

Starting Foundation Work Early

The model code lets a building official issue a permit for the foundation, or any other part of the structure, before the construction documents for the whole house have even been submitted. So site work and the foundation pour can begin legally while the rest of the plans are still being finished, and it isn't a sign of a rushed or unauthorized build. The same section puts the risk on the builder: it proceeds without assurance that a permit for the entire structure will be granted.

Foundation, Rough-In, and Frame Inspections

Three inspections gate the structural core of the home, and each one has to be signed off before the next stage can legally proceed.

Foundation Inspection

This inspection happens after excavation, forms, and any required reinforcing steel are in place, and before concrete is poured. Once concrete goes in, the foundation can't be undone without demolition, so this is the building official's only real chance to check it.

Rough-In Inspections

Plumbing, mechanical, gas, and electrical systems are inspected after they're roughed in, before they're covered by insulation or drywall, and before fixtures and appliances are installed. All of these have to be approved before the frame inspection can happen.

Frame-and-Masonry Inspection

This inspection covers the framing itself, firestopping, and bracing. It can happen only after the rough-in inspections are already approved, making it the last structural sign-off before the walls close up.

Your Pre-Drywall Walkthrough

Under the model code, the plumbing, mechanical, gas, and electrical rough-ins have to be inspected before anything covers or conceals them, and the frame inspection can't happen until those rough-ins are approved. That's what makes the point right before drywall goes up your real last chance to see the framing, plumbing, and wiring inside the walls.

How strictly that's enforced varies locally. In Clark County, Nevada, the building department's own inspections FAQ confirms that placing drywall on even one side of a stud wall before the framing inspection is confirmed is not allowed without prior authorization and justification. It's one concrete example that this isn't just a builder's sales pitch; it's a real code constraint in at least one jurisdiction.

A buyer walkthrough here is not part of the code's inspection process, and nothing schedules it for you. Ask your builder to set one up before drywall goes up, and consider bringing your own inspector or an agent who represents your interests rather than the builder's. For the full system-by-system list to bring with you, see the pre-drywall walkthrough checklist.

Finishes and Local Inspection Add-Ons

After framing is approved, work moves to insulation, drywall, interior trim, flooring, cabinetry, paint, and fixtures. The model code gives your local building official authority to make or require any other inspections needed to confirm compliance, on top of the baseline sequence. The code adds one of its own at this stage: where fire-resistance-rated construction is required, that work has to be inspected after the gypsum board or lath is in place but before plaster is applied or the joints and fasteners are taped and finished.

Exactly which inspections apply, and what they're called, is set locally, not nationally. Ask your builder or your local building department which inspections your specific permit requires. Don't assume the baseline sequence above is the complete list where you're building.

Final Inspection and Occupancy

The final inspection happens after all permitted work is complete, and it's the last checkpoint before the home can legally be occupied. Under the model code, a home cannot be legally used or lived in until the building official issues a certificate of occupancy.

Temporary vs. Final Occupancy

The model code lets a building official issue a temporary certificate of occupancy before every last item is finished, for whatever period the official sets. That's discretionary, and it isn't offered everywhere.

Clark County, Nevada's published inspections FAQ, for one, states that single-family residences and townhomes there aren't authorized to use a temporary certificate of occupancy at all; it's limited to commercial and multi-tenant projects. Confirm with your own building department rather than assuming a temporary CO is available.

Your Final Walkthrough and Punch List

Before closing, walk the finished home and note anything incomplete or incorrect, your punch list, so the builder can fix it before or shortly after closing.

In practice, final sign-off can involve more than just the building department. Clark County's own published example lists clearances that can come from the fire department, drainage review, the local water district, the sewer or septic authority, and public works, depending on the permit. Ask your builder which agencies your specific final sign-off requires.

FHA Financing: Extra Requirements

If you're financing with an FHA loan, expect additional documentation, per FHA's construction requirements in HUD Handbook 4000.1, on top of the local inspection process above. This section applies to FHA financing specifically, not VA, USDA, conventional, or cash purchases, which weren't verified against an equivalent rule.

FHA classifies a new home by construction status: Proposed Construction if no permanent material has been placed yet, Under Construction until the home is 100 percent complete with no certificate of occupancy issued, and Existing Less Than One Year once it's complete, has a certificate of occupancy issued less than a year ago, and has never been occupied.

The inspection and documentation rules below are what FHA requires for maximum financing, the low down payment loan most new-construction buyers use. A home that's under construction or newly completed is capped at 90 percent loan-to-value unless it meets FHA's pre-approval and documentation requirements.

For proposed construction, your lender must obtain either copies of the building permit and certificate of occupancy, or three inspections, footing, framing, and final, performed on form HUD-92051 by an International Code Council Residential Combination Inspector or Combination Inspector, or by the local authority with jurisdiction over the property. Homes already under construction or complete for less than a year have shorter versions of the same requirement. Whichever path applies, your case binder needs:

  • Builder's Certification (HUD-92541): certifies the plans, specifications, and site.
  • Warranty of Completion of Construction (HUD-92544): required in the case binder.
  • 100 percent complete certification (HUD-92900-A): regardless of the inspection process used, your lender must certify on this form that the home is 100 percent complete and meets HUD's minimum property requirements and standards.

The binder also has to show the home was pre-approved (an early start letter or a copy of the building permit issued before construction started), a wood infestation report unless the home sits in an area HUD lists as no to slight infestation risk, and any well water or septic report your local health authority requires. These inspections confirm your home to the lender; they're separate from the schedule that actually releases your construction loan's money. See how the loan's own draw schedule and disbursements work for that side of the process.

Closing on Your New-Construction Home

Your lender must provide your Closing Disclosure at least three business days before your scheduled closing. That's your window to compare the final terms, and any builder-specific line items, against your original Loan Estimate before you sign.

If you combined down payment assistance with a builder incentive, confirm both are reflected correctly on that disclosure. See combining down payment assistance with builder incentives for how that can interact with your closing figures.

Closing also isn't the last word on who actually got paid for the work already done on your home. See why an unpaid subcontractor can still put a lien on your title even after a clean closing for that specific risk and what to ask for beforehand.

Once your certificate of occupancy is issued and your closing documents are signed, the home is legally yours to occupy. One post-closing surprise worth planning for now: your first property tax bill on a new home is often unusually low, because it's assessed on what existed on the state's assessment date, not on your finished house. If you're still shopping, browse new-construction communities by market to see what's available near you.

Frequently asked questions

Can I move into my new home before the certificate of occupancy is issued?
No. Under the model building code, a home can't legally be used or occupied until the building official issues a certificate of occupancy. Whether any temporary occupancy is available at all is set locally: Clark County, Nevada, for example, doesn't offer a temporary certificate of occupancy for single-family homes or townhomes at all, only for commercial and multi-tenant projects.
What is a pre-drywall inspection, and can I be there for it?
It's the point right before insulation and drywall close up the framing, plumbing, and wiring. The building code requires the rough-in inspections to happen before that work is covered, and the frame inspection can't be approved until the rough-ins are, which makes this the practical last chance to see inside the walls. A buyer walkthrough isn't part of that inspection process, so ask your builder to schedule one before drywall goes up.
Do all cities and counties require the same building inspections?
No. Building codes are adopted and enforced locally, so the specific code edition, local amendments, and the exact number and names of required inspections vary by jurisdiction. The baseline sequence (foundation, rough-ins, frame, and final) is a floor that a jurisdiction can add to, since the code itself gives local building officials authority to require additional inspections.
Does financing with an FHA loan add extra requirements during construction?
Yes, for FHA loans specifically. For proposed construction with maximum financing, FHA requires either building permit and certificate of occupancy documentation or three inspections (footing, framing, and final), plus a Builder's Certification (HUD-92541) and a Warranty of Completion of Construction (HUD-92544) in the case binder. Whichever inspection path is used, your lender must also certify on form HUD-92900-A that the home is 100 percent complete. This was verified for FHA only; don't assume VA, USDA, or conventional loans follow the same process.
What's the difference between a temporary and a final certificate of occupancy?
A temporary certificate of occupancy lets part of a project be occupied safely before everything is finished, for a period the building official sets at their discretion. A final certificate of occupancy covers the whole permitted scope. Whether a temporary certificate of occupancy is even available for a single-family home depends entirely on your jurisdiction; Clark County, Nevada, for one, doesn't offer one for single-family homes or townhomes.

Sources

  1. 2021 International Residential Code, Chapter 1: Scope and Administration, International Code Council (ICC Digital Codes) Official source
  2. FHA Single Family Housing Policy Handbook 4000.1, Section II.A.8.i, "New Construction", U.S. Department of Housing and Urban Development Official source
  3. New Residential Construction: Quarterly Starts and Completions by Purpose and Design, U.S. Census Bureau and U.S. Department of Housing and Urban Development Official source
  4. Building Department Inspections FAQ, Clark County, Nevada (Department of Building & Fire Prevention) Official source
  5. Closing Disclosure explainer, Consumer Financial Protection Bureau Official source

About the author

Lexy Glassman is a Nevada Broker-Salesperson (license BS.0144219, licensed since 2013) and VP of Development and Compliance at Platinum Real Estate Professionals, where she built the brokerage's state-compliance systems and mentors and trains agents daily. She is an elected member of the Las Vegas REALTORS® Board of Directors (2025–2026), a two-time GLVAR Young Professionals Network "40 Under 40" honoree, and a YPN Hall of Fame member. She leads The Glassman Group — rated 5.0 across 83 team reviews on Zillow, with 222 team sales — serving Las Vegas, Henderson, and Utah, and works with buyers, sellers, relocations, and military families. A second-generation REALTOR® who grew up in the business and a UNLV marketing graduate who serves on the Lee Business School Corporate Advisory Board, she writes about pricing, negotiations, and the closing process because enforcing how closings are done right is her day job.

Home Stimulus is a new-construction marketplace and homeowner toolkit; articles may reference its 1% listing service performed by licensed partner agents, its cash-offer option, and agent matching.

Ready to make your move?

Put the guidance to work: get a no-obligation cash offer on the home you're leaving, or list it for 1%.