An unfinished driveway, landscaping, or punch-list repair does not have to delay your new-construction closing. Here is how a lender-held completion escrow works under conventional, FHA, and VA rules.

A photograph of a woman looking at an unfinished corner of a new room, with flat hand drawn money-green illustrations of house, dollar signs, clock drawn over it.

A completion or repair escrow lets your new-construction closing and loan funding proceed even though an item like landscaping, a driveway, or a punch-list repair is not finished, as long as the home itself is already complete enough to be lived in safely (HUD Handbook 4000.1, Section II.A.6.viii). The lender holds back part of the sale proceeds to cover the unfinished work instead of delaying the closing date.

Fannie Mae conventional loans, FHA loans, and VA loans each publish their own explicit rule for how much gets held back and how long the builder has to finish (Fannie Mae Selling Guide B4-1.2-05; HUD Handbook 4000.1; VA Lenders Handbook M26-7). The rules differ enough that which loan you have changes the math.

What an Escrow Holdback Is

An escrow holdback is money withheld from the seller's or builder's proceeds at closing, placed in a custodial account the lender establishes, and released once the postponed work is done and verified (Fannie Mae Selling Guide B4-1.2-05). It is not a price discount to you. It is the loan program's condition for letting a mortgage close on a house that is not fully complete, and the lender sets it up.

This is different from a resale buyer's repair credit, which comes from your purchase contract rather than a lender rule. See the contract-based version of this problem on a resale purchase if that is your situation instead.

It's also a different pool of money from what you paid the builder directly before closing. See how a builder's deposit schedule and construction draws actually work for that separate, buyer-funded track.

The Line an Escrow Can't Cross

Each program draws a line before it will allow a completion escrow, and each draws it in its own words. Escrowing funds for a missing driveway is one thing; escrowing funds because the house cannot be occupied is another.

  • FHA: allows a repair escrow only when the property is habitable and safe for occupancy at the time of loan closing (HUD Handbook 4000.1, Section II.A.6.viii).
  • VA: requires that construction of the dwelling itself be complete and the house suitable for immediate occupancy before an escrow for postponed items can even be set up (VA Lenders Handbook M26-7, Chapter 9, Topic 10).
  • Fannie Mae: requires that the postponed items be part of the sales contract, be postponed for a valid reason, and not affect the ability to obtain an occupancy permit. It also caps the cost of the remaining work at 10% of the "as completed" appraised value (Fannie Mae Selling Guide B4-1.2-05).

What Typically Gets Postponed

VA's handbook lists the kinds of items that commonly qualify, when the delay is caused by weather or something else outside the builder's control: walkways, driveways, retaining walls, exterior painting, landscaping, and garages (VA Lenders Handbook M26-7, Chapter 9, Topic 10). These are exterior, non-structural items, not core construction.

Conventional Loans: Fannie Mae's Rule

For a conventional loan sold to Fannie Mae, the lender must withhold 120% of the estimated cost to complete the postponed work from the proceeds due at closing. If the builder offers a guaranteed fixed-price completion contract instead, the escrow only needs to equal that contract price (Fannie Mae Selling Guide B4-1.2-05, effective 2025-12-10).

The work has to be finished within 180 days of the note date, and the delay has to have a valid reason behind it, with inclement weather and a shortage of building materials given as the examples. The items also have to be part of your sales contract, and Fannie Mae will not accept third-party contracts for them (Fannie Mae Selling Guide B4-1.2-05).

What Releases the Escrowed Funds

The escrow has to sit in a custodial account that meets Fannie Mae's criteria, with a signed escrow agreement between lender and borrower spelling out how the money will be managed and paid out. Once the lender obtains a satisfactory Form 1004D, or an accepted completion alternative, it must release the final draw, including any funds left over after the work is paid for (Fannie Mae Selling Guide B4-1.2-05).

The Title-Insurance Catch

Fannie Mae also requires a final title report showing no outstanding mechanic's liens and no exceptions tied to the postponed improvements or the escrow agreement. If the title report comes back before the work is actually finished, the lender has to obtain a title endorsement that protects the priority of Fannie Mae's lien in the meantime (Fannie Mae Selling Guide B4-1.2-05).

FHA Loans: the Repair Completion Escrow

FHA takes a different approach than Fannie Mae's fixed percentage. A mortgagee can set up a repair escrow for incomplete construction, or for alterations and repairs that cannot be finished before closing, but the escrowed funds have to be sufficient to cover the full cost of the work, and the value of the borrower's own labor cannot be counted toward it (HUD Handbook 4000.1, Section II.A.6.viii).

The paperwork is specific:

  • Form HUD-92300, the Mortgagee's Assurance of Completion, is what the lender executes to establish the escrow.
  • Form HUD-92051, the Compliance Inspection Report, is what certifies the work is actually finished.
  • An Escrow Closeout Certification in FHAC is required within 30 days after the escrow account closes, for FHA case numbers assigned on or after October 31, 2016 (HUD Handbook 4000.1, Section II.A.6.viii).

VA Loans: the 150% Rule

On a VA loan, the lender withholds one and a half times, 150%, the third-party-estimated dollar amount needed to finish the postponed items, from the proceeds due the seller at closing (VA Lenders Handbook M26-7, Chapter 9, Topic 10). That is a higher withholding ratio than Fannie Mae's 120%.

VA also requires that the postponement be beyond the builder or seller's control, and that its duration not be unreasonable, which VA describes as usually 90 to 120 days.

The $2,500 Landscaping Exception

VA does not require any escrow at all when the only incomplete work is landscaping, the delay is caused by inclement weather, the estimated cost to finish it is $2,500 or less, and there is adequate assurance the work will get done on time (VA Lenders Handbook M26-7, Chapter 9, Topic 10). Below that threshold, the closing simply proceeds.

No prior VA approval is needed to set up a VA completion escrow. The lender documents it with its own agreement or VA Form 26-1849, and certifies completion with VA Form 26-1839, or, for minor non-structural work, a written lender certification plus the veteran-purchaser's own statement of satisfaction.

Using a Letter of Credit Instead of Cash

A commercial letter of credit can substitute for a cash escrow, as long as it is worth at least 150% of the estimated completion cost, is irrevocable, and stays valid at least six months beyond the completion date (VA Lenders Handbook M26-7, Chapter 9, Topic 10).

Comparing the Three Programs

Escrow holdback as a percentage of completion cost
Fannie Mae (conventional)120%
VA150%

FHA sets no fixed percentage; it requires the escrow to cover the full cost of the work. Sources: Fannie Mae Selling Guide B4-1.2-05; VA Lenders Handbook M26-7, Ch. 9, Topic 10.

ProgramHoldback amountCompletion windowKey form
Fannie Mae (conventional)120% of estimated cost, or the fixed-price contract amount180 days from the note dateForm 1004D
FHAFull cost of the work (no fixed percentage)Not specified as a fixed window in this handbook sectionForm HUD-92300 / HUD-92051
VA150% of estimated costUsually 90 to 120 daysVA Form 26-1849 / 26-1839

One scope note on the conventional column: the 120% and 180-day figures come from Fannie Mae's Selling Guide, so they govern a loan being sold to Fannie Mae. Not every conventional loan ends up there. Ask your loan officer which investor's guide your file is being underwritten to before you assume those numbers apply to you.

How This Shows Up on Your Loan Paperwork

Most closed-end construction loans secured by real property are covered by the same federal Loan Estimate and Closing Disclosure rules, known as TRID, as any other mortgage (CFPB TILA-RESPA Integrated Disclosure FAQs, "Construction loans" topic). You are not signing a different kind of disclosure package because part of the home is unfinished.

Federal disclosure rules give lenders some flexibility in how they document a construction-to-permanent loan: they can treat the construction and permanent phases as one combined transaction, or issue two separate sets of Loan Estimates and Closing Disclosures. Regulation Z's Appendix D also gives lenders specific methods for estimating figures when the draw schedule is not fixed yet.

For new-construction purchases where the lender reasonably expects settlement more than 60 days after the original Loan Estimate, the lender may send a revised Loan Estimate any time up to 60 days before closing, but only if the original Loan Estimate specifically disclosed that possibility (CFPB TILA-RESPA Integrated Disclosure FAQs, "Construction loans" topic).

The holdback also has its own paperwork. On a Fannie Mae loan, the lender and borrower must execute an escrow agreement stating how the escrow account will be managed and how the funds will be disbursed (Fannie Mae Selling Guide B4-1.2-05). Ask your lender to walk you through that agreement alongside your Closing Disclosure, and to point at exactly where your held-back dollars appear, before you sign anything at the closing table.

If the Builder Never Finishes the Work

VA lenders are responsible for making sure postponed work actually gets completed, and VA runs random post-closing monitoring on closed loans to check (VA Lenders Handbook M26-7, Chapter 9, Topic 10). The holdback is not a one-time formality; the lender stays on the hook for follow-through.

On a Fannie Mae loan, if the final title report is issued before the postponed work is done, the lender has to obtain a title endorsement to protect Fannie Mae's lien priority, and the report cannot show outstanding mechanic's liens tied to the unfinished work (Fannie Mae Selling Guide B4-1.2-05).

Beyond these loan-program mechanics, a buyer's practical remedy against a builder who stalls runs through the purchase contract and state consumer-protection or contractor-licensing channels, which vary by state and are outside the scope of these federal rules.

Escrow Holdback vs. Resale Repair Credit

A new-construction completion escrow and a resale repair credit solve a similar-feeling problem in very different ways. The escrow described in this article is a lender and loan-investor requirement, governed by Fannie Mae, FHA, or VA rules, with specific dollar and time limits set by the loan program itself.

A resale repair credit, by contrast, comes from your purchase contract with the seller, not from a federal loan-program rule. If you are buying an existing home and the seller has not completed agreed-upon repairs before closing, read what to do when a seller skips agreed repairs instead, since the remedies and deadlines there run through your contract language rather than the mechanisms in this article.

Before you get to this point, your final walkthrough checklist and documenting a punch list before you sign are the steps that surface exactly which items are unfinished in the first place. And if the builder's delay goes beyond a punch-list item to missing the completion date entirely, see what happens if the builder misses the completion date entirely for that separate scenario.

Frequently asked questions

Can I close on a new home if the landscaping or driveway isn't finished yet?
Generally yes. A lender can escrow funds to cover the specific unfinished item rather than delay closing, but only when the home itself is already complete enough to be safely occupied. This mechanism is called a repair or completion escrow.
How much does a conventional (Fannie Mae) lender have to hold back for unfinished work?
120% of the estimated cost to complete the postponed improvements, unless the builder offers a guaranteed fixed-price completion contract, in which case the escrow only has to equal that contract price. The work must be finished within 180 days of the note date.
How much does a VA loan hold back, and for how long?
150% of the third-party-estimated completion cost, with VA describing a reasonable completion window as usually 90 to 120 days. If the only unfinished item is landscaping and the estimated cost is $2,500 or less, VA requires no escrow at all.
What paperwork does an FHA repair escrow require?
The lender executes Form HUD-92300 (Mortgagee's Assurance of Completion) to establish the escrow, and certifies completion on Form HUD-92051 (Compliance Inspection Report). For FHA case numbers assigned on or after October 31, 2016, the lender must also complete an Escrow Closeout Certification within 30 days after the escrow account closes.
Will the escrow holdback show up as its own line on my Closing Disclosure?
TRID covers most construction loans the same way it covers any mortgage, and gives lenders specific disclosure options for construction-to-permanent loans. Whether the holdback itself gets a dedicated Closing Disclosure line, separate from your escrow agreement, was not confirmed in the sources reviewed for this article; ask your lender to show you exactly where it appears in your paperwork.
What happens if the builder never finishes the postponed items?
On VA loans, the lender stays responsible for making sure the work gets completed, and VA runs random post-closing monitoring to check. Beyond the federal loan-program mechanics, a buyer's practical remedy runs through the builder's purchase contract and state consumer-protection or contractor-licensing channels, which vary by state.

Sources

  1. B4-1.2-05, Requirements for Verifying Completion and Postponed Improvements, Fannie Mae Official source
  2. Handbook 4000.1, FHA Single Family Housing Policy Handbook, Section II.A.6.viii, Repair Completion Escrow Requirement, U.S. Department of Housing and Urban Development (HUD) Official source
  3. VA Lenders Handbook M26-7, Chapter 9: Legal Instruments, Liens, Escrows, and Related Issues, Topic 10, Escrow for Postponed Completion of Improvements, U.S. Department of Veterans Affairs (VA) Official source
  4. TILA-RESPA Integrated Disclosure FAQs, Construction loans topic, Consumer Financial Protection Bureau (CFPB) Official source

About the author

Lexy Glassman is a Nevada Broker-Salesperson (license BS.0144219, licensed since 2013) and VP of Development and Compliance at Platinum Real Estate Professionals, where she built the brokerage's state-compliance systems and mentors and trains agents daily. She is an elected member of the Las Vegas REALTORS® Board of Directors (2025–2026), a two-time GLVAR Young Professionals Network "40 Under 40" honoree, and a YPN Hall of Fame member. She leads The Glassman Group — rated 5.0 across 83 team reviews on Zillow, with 222 team sales — serving Las Vegas, Henderson, and Utah, and works with buyers, sellers, relocations, and military families. A second-generation REALTOR® who grew up in the business and a UNLV marketing graduate who serves on the Lee Business School Corporate Advisory Board, she writes about pricing, negotiations, and the closing process because enforcing how closings are done right is her day job.

Home Stimulus is a new-construction marketplace and homeowner toolkit; articles may reference its 1% listing service performed by licensed partner agents, its cash-offer option, and agent matching.

Ready to make your move?

Put the guidance to work: get a no-obligation cash offer on the home you're leaving, or list it for 1%.

The Home Stimulus app

Your next home, in your pocket.

Search every new-construction home we track, watch builder incentives move, and get an alert the moment a price drops.