Change Orders on a New Build: Cutoff Dates, Fees, and Delays
You can usually still change a selection after signing, but only until your builder's private cutoff for that category of work. Whether "get it in writing" is a legal requirement or just good practice depends on your state, and a change made after your appraisal can affect your lender's completion sign-off.

Yes, you can generally still change a selection after you sign a new-construction contract, up until your builder's cutoff date for that category of work. What it costs depends on your builder's own contract, since no government agency prices or caps a change-order fee. Your real protection is getting the change, and its price, written into a signed change order before the work starts.
What You Can Still Change After Signing
A change to a signed new-construction contract becomes a documented part of the deal once it is written down as a change order and signed by both sides. Several states write that writing-and-signature step directly into their contractor-licensing law, which means a verbal "yes" from the sales office is not the same thing as a binding change.
Two Gates Decide What's Possible
Two separate things control whether you can still make a change, and they are not the same gate.
- The builder's own cutoff schedule. This is a private contract term set by
your builder's construction sequencing, not by any law. It is covered next.
- State contractor-licensing law. In some states, a change to a
construction contract has to be in writing and signed by both parties, and skipping that step is a licensing problem for the contractor. That variation is covered below, in "Get It in Writing."
If your build is still a set of plans rather than a physical structure, more is usually open. See the difference between a spec home, a to-be-built home, and a quick move-in for how much room you actually have to change things at your stage.
The Builder's Cutoff Schedule
Builders lock in selections in stages as construction moves forward, because reversing a decision after it's built means undoing completed work. No government source sets a standard timeline for this. It is set entirely by your builder's own contract and addenda, and it varies by builder and by community.
Structural and Mechanical Cutoffs
Framing, plumbing rough-in, and electrical rough-in are the work that becomes physically irreversible earliest, which is why builders tend to close those categories first. Changing any of them after the walls are framed or the rough-in is inspected means demolition and rework, not a simple substitution. Ask your builder for the specific cutoff dates for structural and mechanical changes in writing when you sign, since this schedule is not standardized and will not appear in any outside source.
Cosmetic Selections Stay Open Longer
Finish-level choices, such as flooring, cabinet color, and fixtures, are typically installed near the end of the build, so builders usually keep that window open longer. "Usually" is doing real work in that sentence: your builder's own selection schedule, not a general rule, is what governs your specific cutoffs.
Get It in Writing: State Law Varies
There is no federal law governing the procedure, timing, or cost of a change order on a private new-home purchase contract. State law fills that gap, and states take genuinely different approaches.
States That Require a Written Order
California and Virginia both put the writing-and-signature step into their contractor law rather than leaving it to the parties, and Virginia attaches a disciplinary consequence when a licensee skips it.
- California (Business and Professions Code § 7164, operative since
2012-07-01): every contract between an owner and a contractor for the construction of a single-family dwelling the owner will keep for at least a year, "and any changes in a contract," has to be evidenced in writing signed by both parties. Read the fine print on which California statute applies to you: § 7159, amended effective 2026-01-01, is the one that spells out that a change order must state the scope of the work, the amount added to or subtracted from the contract, and the effect on progress payments or the completion date, but it governs home improvement contracts, meaning work on an existing home under § 7151, not original construction.
- Virginia (18VAC50-22-260, amended 2025-09-01): the Board for
Contractors lists a licensed contractor's "failure to obtain written change orders, which are signed by both the consumer and the licensee or the licensee's agent, to an already existing contract" as a prohibited act that exposes the contractor to discipline.
States With a Different Approach
Ohio's Home Construction Service Suppliers Act (Revised Code § 4722.02, effective 2012-08-31) does not require a signed change order for every modification. It requires a written base contract once the job costs $25,000 or more, and separately, once reasonably unforeseen but necessary excess costs exceed $5,000 over the life of the contract, it requires the supplier to give the homeowner an estimate of those excess costs, written or oral according to the homeowner's stated preference in the contract, before proceeding.
| State | Legal basis | What triggers protection |
|---|---|---|
| California | Bus. & Prof. Code § 7164 | Any change to an owner-contractor contract to build a single-family home |
| Virginia | 18VAC50-22-260 (Board for Contractors) | Any modification to the existing contract |
| Ohio | Rev. Code § 4722.02 | Unforeseen excess costs over $5,000 |
One structural caveat before you lean on any of these: they are written for a construction contract between an owner and a licensed contractor. Buying a finished or nearly finished production home is often a real-estate purchase agreement instead, and whether a given state's contractor rules reach your paperwork depends on how your deal is structured. That is a question for an attorney licensed where you are building, not one this article can answer for you.
These three states show the range, not the full picture. Confirm the rule in your own state before you rely on a verbal promise, and treat "get it in writing" as a best practice everywhere even where it is not a legal mandate.
The Lender's Problem: Your Appraisal
A change order does not just affect your builder relationship. If your loan is being sold to Fannie Mae, it can affect how your lender has to sign off on the finished home.
The Appraisal Assumes a Finished Home
An appraisal on a new-construction home is based on a specific set of plans and features at the time it's ordered. A change order that alters scope after that point means the finished home may not match what the appraiser assumed, which is why lenders need a way to confirm what actually got built. See what happens when a new-construction appraisal comes in below contract for the related scenario of the appraisal itself falling short.
Form 1004D and the Completion Sign-Off
The Appraisal Update and/or Completion Report, Form 1004D, is the form Fannie Mae's Selling Guide uses to confirm that conditions noted in the original appraisal, including completion of construction, have actually been met on one- to four-unit properties. Interior photos of the completed home may be taken at the completion inspection and included with the report.
For a loan a lender intends to sell to Fannie Mae, the Selling Guide requires the lender to verify completion, via Form 1004D or an accepted alternative such as a borrower and builder attestation letter carrying exterior and interior photos, before the loan can be sold. This applies regardless of the property's state, because it is a Fannie Mae investor requirement, not a state law.
The Postponed-Improvements Limit
Fannie Mae will let a loan close with specific items still unfinished only if all of the following hold:
- The postponed items are part of the sales contract, not an informal
add-on or a third-party contract.
- They are postponed for a valid reason, such as inclement weather or a
shortage of building materials, and they do not affect the ability to obtain an occupancy permit.
- They add up to no more than 10% of the home's "as completed" appraised
value.
- They are completed within 180 days of the note date.
- A completion escrow is funded at 120% of the estimated cost to finish
them.
If a change order pushes part of your home's completion past your closing date, this is the framework your lender has to work within, not a case-by-case judgment call. Buyers using FHA, VA, or USDA financing should not assume this exact rule applies to them; see the extra builder paperwork FHA, VA, and USDA loans require for those programs' own new-construction requirements.
Permits: A Change May Need Approval
A structural or floor-plan change can trigger more than a new price. It can also require the building department to approve the change before work continues.
When a Permit Revision Is Needed
Permit-revision requirements are set entirely by the local building department, city or county, not by state or federal law, so there is no national standard to point to. The City of Los Angeles Department of Building and Safety, for example, lists a separate "Pay Modification Fees" service among its online plan-review and permitting tools.
A dedicated payment channel like that suggests modifying a permit is handled as its own fee-bearing step rather than folded into the original permit, but it is one example from one city, not a majority pattern, and the department's page does not publish the triggers or the amounts. Ask your builder or your local building department directly whether your change needs a permit revision, since this genuinely varies by jurisdiction.
What a Change Order Typically Costs
There is no government-set price list for a change order, and no Tier-1 source publishes a typical dollar amount, because a builder's change-order fee is a private contract term.
The Price of the Work Itself
The builder sets the number: the cost difference for the changed item, plus whatever administrative or processing charge its contract allows. None of the state laws above caps that amount, which is why the signed document is the only thing that pins the price down.
California shows what a well-drafted change order contains. On a home improvement contract, § 7159 requires the order to state the amount added to or subtracted from the contract price. That requirement does not reach original construction, but the standard it sets is the one to insist on whatever you are building: the dollar figure in the document, not a verbal quote from a sales rep.
Costs a Change Order Can Trigger
A change order's sticker price is rarely the only cost. Depending on what you change, it can also trigger:
- A permit-revision fee from your local building department, in an amount
set locally and not published in any national source.
- A shift in your completion date or progress-payment schedule, which
California requires a home improvement change order to spell out and which is worth asking for in writing on any build.
- A lender-side completion check if the change happens after your
appraisal was ordered and your closing depends on Fannie Mae's postponed-improvements framework described above.
The Bottom Line
Treat a post-signing change as three separate questions, not one negotiation. First, confirm your builder's cutoff window for that category of work; it is a contract term, so ask for it in writing. Second, get the change itself written and signed before any work starts, with the price stated in the document. Several states require the writing and the signatures by law, and the price line is worth insisting on everywhere regardless.
Third, if the change comes after your appraisal was already ordered, ask your lender how it affects completion verification and whether it fits within the postponed-improvements limits.
A change order is a request you make. When the builder is the one initiating the swap instead, typically under a substitution clause for a comparable material or appliance, a different standard applies; see what actually limits a builder's right to substitute materials without asking you first for that side of the question.
See the full new-construction buyer's guide for the rest of the process, or your rights if you need to cancel the contract instead of changing it.
Frequently asked questions
- Can I still change a selection after I sign my new-construction contract?
- Yes, generally, until your builder's cutoff for that category of work. Treat any verbal yes from the sales office as non-binding until it becomes a signed, written change order stating the scope, the price change, and any effect on your completion date. In several states, a written change order signed by both sides is a legal requirement in a construction contract with a licensed contractor, not just good practice.
- Does every state legally require a written, signed change order?
- No, it varies by state. California's contractor law requires every contract, and any change to it, for the original construction of a single-family dwelling the owner keeps at least a year to be in writing signed by both parties, and Virginia's Board for Contractors treats a licensee's failure to obtain a written, dual-signed change order as a prohibited act. Ohio's home-construction law instead requires a cost estimate once unforeseen but necessary excess costs cross a $5,000 threshold, not a signed order for every change. Confirm the rule where you're building.
- What happens to my mortgage if I change something after the appraisal is done?
- If your loan is being sold to Fannie Mae, your lender has to verify the home was finished the way the appraisal assumed, using Form 1004D or an accepted alternative, before the loan can be sold. If part of the home is still unfinished at closing, that's allowed only if it's in the sales contract, worth no more than 10% of the as-completed appraised value, finished within 180 days of the note date, and backed by a completion escrow funded at 120% of the estimated finish cost.
- Do I need a new building permit if I change my floor plan or a structural feature?
- Possibly. Permit-revision rules are set by your local building department, not by state or federal law, so the answer depends on where you're building. Some departments handle changes to an issued permit as their own fee-bearing step: Los Angeles, for example, lists a separate 'Pay Modification Fees' service. Ask your builder or your local building department directly rather than assuming.
- Who has to sign a change order for it to count?
- In states that regulate this directly, both sides have to sign. Virginia's rule names the consumer and the licensee or the licensee's agent, and California requires changes to an original-construction contract to be in writing signed by both the owner and the contractor. Getting those signatures before the changed work starts is the safe practice everywhere, and it is what California's home improvement rule requires on remodeling work, so check your own state's rule before assuming a verbal confirmation is enough.
- What does a change order usually cost?
- There's no government-set price list. The builder sets the number: the cost of the changed item plus whatever administrative or processing charge its contract allows. None of the state laws reviewed here caps that amount, so the signed change order itself is your real protection. California spells out that a change order on a home improvement contract has to state the amount added to or subtracted from the price, which is a good model for what to insist on in writing before you agree, whatever you're building.
Sources
- B4-1.2-05, Requirements for Verifying Completion and Postponed Improvements, Fannie Mae Selling Guide Official source
- B4-1.2-01, Appraisal Report Forms and Exhibits, Fannie Mae Selling Guide Official source
- California Business and Professions Code Section 7164 (contracts for original construction of a single-family dwelling), California Legislative Information (official state statute) Official source
- California Business and Professions Code Section 7159 (home improvement contracts, change orders and extra work), California Legislative Information (official state statute) Official source
- 18VAC50-22-260, Board for Contractors regulations, grounds for disciplinary action (change orders), Virginia Law / Virginia Board for Contractors (Dept. of Professional and Occupational Regulation) Official source
- Ohio Revised Code Section 4722.02 (Home Construction Service Suppliers Act, service contract requirements), Ohio Revised Code (official, Ohio Legislative Service Commission) Official source
- Los Angeles Department of Building and Safety, online services (permit modification fees), City of Los Angeles Department of Building and Safety Official source