Taxes, Rules & OwnershipPart of: The New-Construction Home Buyer's Guide
Statutes of Repose: The Deadline That Ends a Construction-Defect Claim
A statute of repose is an absolute deadline for suing your builder over a construction defect, and it starts ticking at a fixed construction event, not at the day you find the problem. Here is how that clock differs from a statute of limitations, nine verified state deadlines ranging from 5 to 10 years, and whether sending a required repair notice buys you more time.

A statute of repose is an absolute deadline for suing a builder over a construction defect, and it keeps running whether or not anyone has found the defect yet. Across the nine states whose statutes are verified below, that deadline runs out somewhere between 5 and 10 years after the construction event the state measures from. This guide is part of the new-construction buyer's guide.
The Short Answer
A statute of repose runs from a fixed construction event, usually substantial completion of the home, not from the day a defect is discovered. The U.S. Supreme Court described the mechanism directly in CTS Corp. v. Waldburger: a repose period "is not related to the accrual of any cause of action," so it can run out before an injury or defect even exists, let alone gets found.
That is the opposite of how a statute of limitations works. A limitations period usually starts when a claim accrues, typically at discovery of the problem. A repose period ignores discovery entirely and just counts down from the construction event itself, so it can close a claim years before anyone notices anything is wrong.
Repose vs. Limitations: Two Clocks
Why discovery doesn't restart the clock
Finding a defect years after move-in does not reopen or extend a repose deadline. The clock started at construction and keeps moving on that schedule regardless of when, or whether, you notice a problem.
That is a hard distinction from the more familiar idea of a filing deadline that "starts when you find out." A repose deadline was already running before you had any reason to look.
Two clocks, one claim
Several states run two different clocks on the same claim: a shorter, discovery-based limitations period operating inside a longer, fixed repose period. North Carolina's statute frames this directly, describing its 6-year repose period as an outside limitation within which the state's ordinary discovery-based limitations periods must operate.
Florida uses the same structure with different numbers. A 4-year limitations period runs from when you discover, or reasonably should have discovered, a latent defect, sitting inside a 7-year repose period that runs from the certificate of occupancy, the certificate of completion, or the date construction was abandoned, whichever is earliest. The action is barred after 7 years no matter when the defect was actually found.
How Long You Actually Have
What starts the clock
Most of the states verified for this guide start the repose clock at substantial completion of the home, but the trigger event is not identical everywhere.
- Substantial completion: the trigger used in California, Texas, Arizona, Ohio, Nevada, and (together with the builder's last act) North Carolina.
- Certificate of occupancy or completion: Florida instead starts its clock at whichever comes first among the certificate of occupancy, the certificate of completion, or the date construction was abandoned.
- Termination of services: Washington starts its 6-year clock at substantial completion or termination of the professional's services, whichever is later.
- Performance of the work itself: Virginia measures its 5 years from when the design, planning, surveying, supervision, or construction services were performed, not from a completion date.
Closing on the house is not the trigger anywhere in this pack. For a spec or quick-move-in home in particular, substantial completion (or Florida's certificate of occupancy) can predate your closing date by weeks or months, so confirm the actual construction date, not the date you signed.
State repose periods compared
The nine states below have primary statutes verified for this guide, spanning repose periods from 5 to 10 years. This is not a 50-state list. For any other state, use the warranty and repose rules by state to confirm your own state's figure rather than assume one of these applies.
| State | Repose period | Trigger event | Notable wrinkle |
|---|---|---|---|
| Texas | 10 years (6 with a qualifying written warranty) | Substantial completion | On a residence, a contractor's written warranty meeting the statute's 1/2/6-year minimums shortens the deadline to 6 years; a governmental entity suing has its own 8-year period |
| Nevada | 10 years | Substantial completion | No outer time limit at all for a claim based on fraud |
| Ohio | 10 years | Substantial completion | A defect discovered in the final 2 years of the window still gets 2 years from discovery to sue |
| California | 10 years | Substantial completion, and no later than recordation of a valid notice of completion | The Right to Repair Act's outer limit states no exception for later discovery of the defect |
| Arizona | 8 years (9 if discovered in year 8) | Substantial completion | Covers contract-based claims, including implied warranty; injury or a latent defect surfacing in year 8 adds 1 year, capped at 9 |
| Florida | 7 years | Certificate of occupancy, certificate of completion, or abandonment, whichever is earliest | A 4-year discovery-based limitations period runs inside the 7-year outer bound |
| North Carolina | 6 years | Later of substantial completion or the builder's last act or omission | Statute frames the 6 years as the outer boundary containing ordinary limitations periods |
| Washington | 6 years | Substantial completion or termination of services, whichever is later | An ongoing service relationship can push the trigger date later |
| Virginia | 5 years | Performance of the design or construction services | Shortest period verified here; measured from when the work was done, not from completion |
Each figure above traces to that state's own construction-defect repose statute; see the sources below. If a state you need is not listed, do not assume it falls in this range. Look it up.
Right-to-Repair Notice and the Clock
Some states, California and Florida among them, require a written pre-suit notice to the builder before a defect suit can proceed, a step covered in the written notice you may have to send before you can sue. Whether sending that notice affects your repose deadline is state-specific.
California: notice extends the window
California's Right to Repair Act sets out a pre-suit claim process, and going through it changes your filing deadline rather than simply pausing it. If the applicable filing deadline would otherwise run out while that process is under way, the statute extends it to 100 days after the repair is completed, or to 45 days after the builder's window for responding to the notice of claim expires without action.
That extension is written into the Right to Repair Act itself, and so is California's 10-year outer limit. The code applies ordinary tolling law to the title's filing periods, and it singles out that 100-day and 45-day extension as the exception to its rule that repairs made under the pre-suit process do not extend the period for filing an action. What the California sections cited here never state is whether the notice process can carry a claim past the 10-year mark, so treat that as a question for a lawyer rather than a settled answer.
Florida: notice pauses limitations
Florida's Chapter 558 pre-suit notice works differently. Serving the required written notice of claim tolls the ordinary statute of limitations, but the statute is explicit that it does not touch the outer deadline: a notice of claim served under the chapter "shall not toll any statute of repose period" under Florida's repose statute.
In practice, a Florida homeowner can send the required pre-suit notice and still lose the underlying claim if the 7-year repose deadline runs out while the notice process is still playing out. Florida settles that question in one sentence of statute; California's cited sections never address it in those terms. Two states, two different levels of certainty on the same question, which is the clearest sign in this pack that you cannot assume a required notice buys you extra time against repose.
If You're Past Year One
The clock runs before you notice
Because a repose period runs from a fixed construction event rather than from discovery, every year that passes after your home was finished uses up part of your window, whether or not you have found a problem. A homeowner who has never had an issue is losing time against the deadline at the same pace as one already dealing with a leak or a cracked foundation.
If you are inspecting an aging new-construction home for early warning signs, keep a dated, written record of problems as you find them. It matters for a warranty claim well before repose becomes the live issue.
Confirm your own state first
Filing deadlines vary by claim type, and missing the one that applies lets the other side ask the judge to dismiss your case even if you had a good case, according to the Judicial Branch of California's own self-help guidance for people preparing to sue. That guidance lists different deadlines for different kinds of California cases, and it works through a contractor who broke a pipe and flooded a home as its example of a property-damage claim.
The fraud exception is narrow, not a general escape hatch. Nevada, for one, sets no outer time limit for a claim based on fraud, but that still requires proving fraud, not just a defect that went unfixed.
Check Your State, Then Act
The 9 states verified here span 5 to 10 years and several different trigger events, so there is no single national number to remember. Start with the state-by-state repose-deadline lookup to find your own state's period and trigger event before you assume you are inside, or outside, your window.
A few related next steps, depending on where you are in the process:
- Filing a claim: filing a builder warranty claim walks through the practical filing process.
- What your warranty covers: what a 1-2-10 warranty's ten-year term actually covers explains how warranty coverage differs from the repose deadline itself.
- Selling before the window closes: see what happens to these deadlines if you sell the home.
- Another clock tied to the trades who built your home: an unpaid subcontractor can still record a lien against your title long after a clean, fully-paid closing; see how lien waivers protect you from that specific claim.
- If the builder's own entity is gone: how to check whether a dissolved, project-specific LLC is still suable, and who else might be reachable covers that question separately from the repose deadline itself.
If you are trying to work out where you stand on an actual problem, speak with a real estate professional about your specific claim rather than guess from a general guide like this one.
Frequently asked questions
- Is a statute of repose the same thing as a statute of limitations?
- No. A statute of limitations period starts when a claim accrues, usually at discovery of the injury. A statute of repose instead starts at a fixed external event, such as substantial completion of construction, and keeps running whether or not the injury has occurred or been discovered yet.
- I just found a defect from years ago. Can I still sue?
- It depends entirely on whether your state's repose deadline has already passed; discovering a defect does not reopen or extend a repose period. Verified state deadlines in this guide range from 5 to 10 years depending on the state and trigger event, so confirm your own state's rule at the warranty and repose rules by state hub rather than assume a number.
- Does sending my builder a required repair notice pause the deadline?
- It depends on the state, not a single rule. In Florida, the required pre-suit notice tolls the ordinary limitations clock, but the statute explicitly says it does not toll the repose clock. In California, the notice process instead extends the filing deadline forward by a set number of days. Do not assume either result applies to your own state without checking.
- What actually starts the clock? Is it the day I closed on the house?
- No, and this is a common misconception. Most of the states verified in this guide start the clock at substantial completion of construction, which can predate closing, especially for a spec or quick-move-in home. Florida instead starts it at the certificate of occupancy, certificate of completion, or abandonment of construction, whichever is earliest. Find your build's actual substantial-completion or certificate date, not your closing date.
- Is there any construction-defect deadline that never runs out?
- Generally no, once repose passes on an ordinary defect or negligence claim. Nevada is a narrow verified exception: it sets no outer time limit for a claim based on fraud. That is a narrow carve-out that still requires proving fraud, not a general escape hatch, and it should not be assumed to apply in other states.
Sources
- CTS Corp. v. Waldburger, 573 U.S. 1 (2014), syllabus and opinion, Supreme Court of the United States, via Cornell Law School Legal Information Institute Official source
- California Civil Code Section 941 (Right to Repair Act, outer time limit), California Legislative Information, State of California Official source
- California Civil Code Section 927 (effect of pre-litigation notice on filing deadline), California Legislative Information, State of California Official source
- Florida Statutes Section 95.11(3)(b), limitations and repose for actions on construction of an improvement to real property, Florida Legislature / The Florida Senate Official source
- Florida Statutes Section 558.004, notice and opportunity to repair; effect on statute of limitations and statute of repose, Florida Legislature / The Florida Senate Official source
- Texas Civil Practice and Remedies Code Section 16.009, persons furnishing construction or repair of improvements, Texas Legislature Official source
- Arizona Revised Statutes Section 12-552, actions arising out of deficiency in construction of improvement to real property, Arizona State Legislature Official source
- North Carolina General Statute 1-50(a)(5), real property improvements, statute of repose, North Carolina General Assembly Official source
- RCW 4.16.310, actions relating to construction, alteration or repair of improvement upon real property, Washington State Legislature Official source
- Code of Virginia Section 8.01-250, limitation on actions for damages arising from a defective or unsafe improvement to real property, Virginia Division of Legislative Automated Systems Official source
- Ohio Revised Code Section 2305.131, bringing of action for injury, death, or property damage arising from a defective or unsafe improvement to real property, Ohio Legislative Service Commission Official source
- Nevada Revised Statutes 11.202, actions for damages for deficiency in construction of improvement to real property, Nevada Legislature Official source
- Before you sue someone, California Courts Self-Help Guide, Judicial Branch of California Official source